Display Contract DetailsThis page displays the details of the contract.
Visit our detailed help page
or click the
|
| Public Authority | Department of Biodiversity, Conservation and Attractions |
| Address | 17 Dick Perry Avenue, Kensington, WA, Australia, 6151 |
| Title | Wiilman Bilya Stage 1A Walktrail Construction |
| Reference Number | DBCA404WT2162022 |
| Description | DBCA is seeking a suitably qualified Contractor to construct stage 1A of this 5-day walk trail. Stage 1A of the ?Wiilman Bilya? walk trail starts at the Karak Trail in Allanson and travels west along Coalfields Highway for 6.2kms to the westside of Hamilton Causeway where it will link to the previously completed Stage 1 of the walk trail. The works include but are not limited to the following:
|
| Type of Work | Works |
| Procurement Method | Open Advertisement |
| Associated with Tender | |
| UNSPSC 1 | Earthworks engineering - (25%) |
| UNSPSC 2 | Gravel or dirt road construction service - (50%) |
| UNSPSC 3 | Roads and landscape - (25%) |
| Region/s | South West |
| Number of Submissions | 4 |
| Panel Contract | No |
| Contract Term | One Off |
| Closing Date | 11 Mar, 2022 |
| Award Date | 7 Apr, 2022 |
| Commencement Date | 7 Apr, 2022 |
| Initial Expiry Date | 7 Oct, 2022 |
| Final Expiry Date | 7 Oct, 2023 |
| Original Contract Value | $200,000 (Estimate) |
| Actual Contract Expenditure | $196,443 |
| Contract Developer | Raymond Ernest Halse |
| Phone | OFFICE: (08) 92199506
MOBILE: 0417358379 |
| ray.halse@dbca.wa.gov.au | |
| Contract Manager | Jordan Gibbs |
| Mobile | 0436935596 |
| jordan.gibbs@dbca.wa.gov.au |
Actual Expenditure |
|||||
| Expenditure Period: | 07/04/2023 - 06/04/2024 | Expenditure $: | $196,443 | ||
Contractors |
|
| 1) |
T & R Contracting Pty Ltd
7 Sweeney Court
Collie WA Australia 6225 |
|
Comments:
Fixed price components $100,560 Time and materials for trail construction |
|