| Public Authority | Economic Regulation Authority |
| Address | Level 4, 469 Wellington Street, Perth, WA, Australia, 6000 |
| Title | 2023 Benchmark Reserve Capacity Price determination - Power station and associated costs |
| Reference Number | ERA2023172 |
| Description | Technical Advice - 2023 Benchmark Reserve Capacity Price determination - Power station and associated costs |
| Type of Work | Goods and Services |
| Procurement Method | Direct Sourcing |
| UNSPSC 1 | Economic or financial evaluation of projects - (100%) |
| Region/s | Perth Metropolitan |
| Number of Submissions | 1 |
| Panel Contract | No |
| Contract Term | One Off |
| Closing Date | 15 Jul, 2022 |
| Award Date | 18 Jul, 2022 |
| Commencement Date | 18 Jul, 2022 |
| Initial Expiry Date | 7 Dec, 2022 |
| Final Expiry Date | 31 Aug, 2023 |
| Original Contract Value | $41,466 (Estimate) |
| Revised Contract Value | $52,499 (Estimate) |
| Actual Contract Expenditure | $45,888 |
| Contract Developer | Rose Hunt |
| Phone | OFFICE: (08) 65577934 |
| rose.hunt@erawa.com.au | |
| Contract Manager | Richard Cheng |
| Phone | PHONE: (08) 65577947 |
| richard.cheng@erawa.com.au |
Price Variations |
||||||
| Variation Period: | 18/07/2022 - 17/07/2023 | No. of Variations: | 1 | Total Variation $: | $11,033 | |
Actual Expenditure |
|||||
| Expenditure Period: | 18/07/2022 - 17/07/2023 | Expenditure $: | $45,888 | ||
Contractors |
|
| 1) |
GHD Pty Ltd
999 Hay Street
Perth WA Australia 6000 |