Nowergup Depot Upgrade Project - Site Coordinator and Supervisor
|
Public Authority
|
Public Transport Authority |
|
Address
|
116 West Parade, Perth, WA, Australia, 6000 |
|
Title
|
Nowergup Depot Upgrade Project - Site Coordinator and Supervisor |
|
Reference Number
|
PTA190256 |
|
Description
|
In order for the PTA to operate with the assurance that the necessary compliance is being met, the Program & Projects Branch requires site coordination and supervisory services for the delivery and completion phases of construction projects including, but not limited to:
- Nowergup Depot Upgrade Project;
- Crossing the Network – At Grade Pedestrian Crossing Upgrades Project;
- Moore Street Level Crossing Closure Project;
- Claremont Station Project; and
- Stadium Station Signalling Support Services Project.
These project(s) form part of the PTA’s overall Rail Infrastructure Projects and are essential to ensuring the integrity of the PTA’s wider network. These projects are closely related and entail installations, upgrades and renewals of predominately civil and structural infrastructure to many and varied assets across the network over several years.
Working under the direction of the relevant Project Manager on either one or multiples of the aforementioned projects, the Site Coordinator/Supervisor will be required to:
- Provide site coordination and supervisory services for the delivery and commissioning of projects;
- Manage and coordinate project sites to ensure construction operations are maximised and PTA’s contractors and staff operate in a safe and secure working environment;
- Coordinate construction activities for PTA’s contractors and staff;
- Ensure compliance with regulatory and OSH standards;
- Carry out works and compliance inspections of infrastructure works of the assigned project or projects;
- Review and assess contractors’ construction plans (Safe Work Method Statements, Safety Plans, Construction Methodology);
- Report on contractors’ progress on a day to day basis and maintain accurate records including weather conditions, manpower, plant disposition and traffic management;
- Report on the quality of work delivered by contractors’ and produce comprehensive written reports as directed by the program manager / project manager;
- Implement effective risk management strategies including supporting the program manager/ project manager with risk identification, assessment, monitoring, reporting and documentation relating to construction site operations;
- Review and assess inspection and test plans;
- Report conformance to and variance against contractual requirements and progress of works by oral, written and electronic means;
- Conduct inspections for the release of hold points as identified in the contract and related documentation, witness and formally release hold points as directed by the project manager;
- Coordinate and assist in the provision of information / statistics for contract progress reports as required.
- Participate in contract meetings and discussions as required;
- Undertake similar works within the Site Coordinator / Supervisors skill set at the direction of the Program Manager Rail Infrastructure or project managers (as required).
- Coordinate the receipt of plant and materials onto site;
- Act as the point of contact for escorting personnel in and around the construction site;
- Ensure PTA’s contractors and staff are aware of site safety, security and emergency procedures on site.
|
|
Type of Work
|
Goods and Services
|
|
Procurement Method
|
Quotation
|
|
UNSPSC 1
|
Project management - (100%)
|
|
Region/s
|
Perth Metropolitan
|
|
Number of Submissions
|
3
|
|
Panel Contract
|
No
|
|
Contract Term
|
Fixed Period |
|
Closing Date
|
27 Feb, 2019 |
|
Award Date
|
27 Mar, 2019 |
|
Commencement Date
|
27 Mar, 2019 |
|
Initial Expiry Date
|
26 Sep, 2020 |
|
Final Expiry Date
|
26 Sep, 2020 |
|
Original Contract Value
|
$170,500
(Estimate)
|
|
Revised Contract Value
|
$201,502
(Estimate)
|
|
Actual Contract Expenditure
|
$201,502
|
|
Contract Developer
|
Stephanie Woolman
|
|
Phone
|
OFFICE: (08) 93262538
|
|
E-Mail
|
Stephanie.Woolman@pta.wa.gov.au
|
Price Variations
|
| Variation Period: |
27/03/2019 - 26/03/2020 |
No. of Variations: |
1 |
Total Variation $: |
$31,002 |
|
Actual Expenditure
|
| Expenditure Period: |
27/03/2019 - 26/03/2020 |
|
Expenditure $: |
$201,502 |
|
Contractors
|
|
1)
|
Prism Contracting & Consulting (Peter Edward Matthiessen)
2 / 24 Crocker Drive
Malaga WA Australia 6090
|
|
|