Display Contract DetailsThis page displays the details of the contract.
Visit our detailed help page
or click the
|
| Public Authority | Public Transport Authority |
| Address | 116 West Parade, Perth, WA, Australia, 6000 |
| Title | Cannington Station Bus Interchange Modifications - Detailed Design |
| Reference Number | PTA190594 |
| Description | The Scope of Services required includes the delivery of Issued for Construction design deliverables and necessary approvals this project in line with the Concept Design. PTA envisages that the process will be include, but not be limited to:
|
| Type of Work | Goods and Services |
| Procurement Method | Panel
PTA180003 - Network and Infrastructure Consultant Panel - Engineering Services |
| UNSPSC 1 | Professional engineering services - (100%) |
| Region/s | Perth Metropolitan |
| Number of Submissions | 2 |
| Panel Contract | No |
| Contract Term | One Off |
| Closing Date | 30 Jul, 2019 |
| Award Date | 21 Aug, 2019 |
| Commencement Date | 21 Aug, 2019 |
| Initial Expiry Date | 30 Jun, 2020 |
| Final Expiry Date | 30 Jun, 2020 |
| Original Contract Value | $81,807 (Estimate) |
| Revised Contract Value | $87,054 (Estimate) |
| Actual Contract Expenditure | $74,368 |
| Contract Developer | Melissa Thomas |
| Phone | OFFICE: (08) 93265433 |
| melissa.thomas@pta.wa.gov.au |
Price Variations |
||||||
| Variation Period: | 21/08/2019 - 20/08/2020 | No. of Variations: | 1 | Total Variation $: | $5,247 | |
Actual Expenditure |
|||||
| Expenditure Period: | 21/08/2023 - 20/08/2024 | Expenditure $: | $74,368 | ||
Contractors |
|
| 1) |
GHD-Aurecon Joint Venture
999 Hay Street
PERTH WA Australia 6000 |